09.05.2011 00:00 Age: 1 year
CHRONOLOGY of the expansion of GLOBAL HYDRO ENERGY
Here you can find a chronicle of the construction work at the company site in Niederranna
03.07.2009
Ground breaking ceremony: formal start of the building project
November 2009
Beginning of the construction works
December 2009
The foundation is finished
January 2010
After a short interruption, due to an onset of winter, the construction of the production hall started.
April 2010
Connection of the hall under construction with the existing production hall and start of constructing the office building.
June 2010
Delivery of the new machinery for the production
July 2010
Removal of the existing machinery into the new production hall
August 2010
All-out operation in the new manufacturing hall
November 2010
Relocation to the new company building
May 2011
Opening ceremony of the new production hall and the customer center.
|
|
|---|